Capital Project Reliability ROI Ranking
Rank every proposed capital project by expected reliability improvement per dollar spent.
Included in the Utilities pack
$99 /seat/moJoin the waitlistThe pack includes 14 other ready-made workflows.
What it does
Loads the capital project list, joins each to affected circuit segments, estimates SAIDI/SAIFI reduction using asset type and failure rate models, and computes reliability-improvement-per-million-dollars — the prioritization framework that turns a $200M capital plan into a defensible PUC filing.
- Data it uses
- Proposed capital project list with cost estimates (tabular upload)
- Current SAIDI/SAIFI by circuit (from OMS analysis)
- Asset condition scores by circuit
- Customer class mix by circuit (industrial, commercial, residential)
- Specialists on it
- Infrastructure Engineer, Risk & Exposure Analyst, GIS Analyst, Data Engineer
The steps
Each step runs in order and shows its work as it goes. Open a step to read exactly what it asks for.
1Validate project list and map to circuit segments
Upload and validate the capital project file — confirm required fields: project ID, project type (reconductoring, substation upgrade, automated switching, underground conversion, sectionalizing, vegetation management contract), estimated cost, affected circuit IDs, and planned in-service year. Geocode project locations and join to the distribution circuit network. Flag projects where the affected circuit IDs do not match circuits in the GIS network — these may be mis-labeled or reference retired circuits. Report project count and total estimated cost by project type. Flag if total plan cost exceeds {{annual_capex_budget}} — this will require prioritization, and the ROI ranking is the primary tool.2Estimate SAIDI/SAIFI reduction by project type
Apply industry-standard SAIDI/SAIFI improvement factors by project type, adjusted for current circuit performance: (1) Reconductoring deteriorated conductor: 15–25% SAIDI reduction on affected circuit segments; (2) Automated switching (SCADA-controlled): 20–35% SAIDI reduction by reducing restoration time from manual patrol to remote-switching (typical CAIDI reduction of 45–90 minutes per switching zone); (3) Underground conversion of overhead circuit: 60–75% SAIDI reduction (underground SAIDI ~12–15 vs. overhead ~120–150 min/yr); (4) Sectionalizing (additional fuses/reclosers): 10–20% SAIDI reduction by limiting fault exposure; (5) Substation voltage regulator: reduces sag-induced outages by 5–10%. Apply circuit-specific current SAIDI to compute absolute SAIDI minutes saved per project. Flag if a proposed project's affected circuit currently has below-median SAIDI — the improvement opportunity is limited compared to targeting the worst-performing circuits.
3Compute reliability ROI and rank projects
Compute reliability ROI for each project: ROI = (annual_SAIDI_reduction_customer_minutes × customers_on_circuit × value_of_reliability) / project_cost. Use {{value_per_customer_minute:0.005}} dollars per customer-minute as the default value-of-reliability (consistent with EPRI studies; industrial customers value reliability at $2–8/kWh, commercial at $0.50–2/kWh, residential at $0.05–0.20/kWh — if customer mix is available, use a weighted average). Also compute regulatory ROI: SAIDI_minutes_saved_system_total / project_cost_millions — this is the metric PUC staff most commonly uses in rate case review. Rank projects by regulatory ROI descending. Compute a Pareto curve: the minimum set of projects that achieves 50% and 80% of the total potential SAIDI improvement.4QA ROI ranking and assemble citations
Report the top-10 projects by regulatory ROI with their estimated SAIDI improvement, project cost, and ROI score. Report the minimum investment required to achieve the target SAIDI reduction of {{target_saidi_improvement:20}}%. Flag any project with a regulatory ROI below 0.5 customer-minutes-saved per $1,000 invested — projects at this level are unlikely to survive PUC prudency review when higher-ROI alternatives are available. Flag any project type that represents more than 40% of total plan cost — concentration risk in a single project type (e.g., all substation upgrades, all underground conversion) limits the plan's ability to address the diverse reliability drivers identified in the SAIDI/SAIFI analysis. Assemble citation block: SAIDI/SAIFI data vintage, project cost estimate basis and year, EPRI value-of-reliability study reference, asset condition data source and vintage.
More in the Utilities pack
- Vegetation encroachment riskPrioritize trim spend by predicted outage cost.4 steps
- Hydraulic pressure deficiencyFind every node below 20 psi in your water network.3 steps
- Storm outage post-mortemGenerate the regulator-facing post-mortem in one hour.5 steps
- Smart-meter rollout planningSequence your AMI rollout for max early ROI.5 steps
- EV-charger demand forecastForecast every neighborhood's 2030 EV-charger demand.5 steps
- Distribution transformer load riskFind which transformers saturate first as EV adoption grows.5 steps